Recipients of funds for a construction project shall comply with the following bidding requirements:

(a) The bid period shall be not less than 14 calendar days, unless the department has approved a shorter bid period due to an imminent threat to public health or safety;
(b) The advertisement for bids or competitive quotes shall include the following information:
(1) The project name and contract number;
(2) The location of work;
(3) A description of work to be performed;
(4) The time and date at which the bids will be publicly opened and read aloud, and a statement that bids received after that time will not be accepted;
(5) An address and cost information for obtaining plans and specifications; and
(6) The addresses where plans and specifications can be examined;
(c) For projects with estimated construction costs over $100,000, the advertisement shall also include:
(1) A requirement for a bid security in the amount of 5% of the bid in the form of a certified check or a bid bond executed by a surety company authorized to do business in New Hampshire and made payable to the recipient; and
(2) A statement that a 100% performance bond and a 100% payment bond will be required;
(d) The recipient shall reserve the right to:
(1) Reject any or all bids; and
(2) Waive any informalities or minor defects on bids received; and
(e) If any addenda to the bid are needed, the recipient shall:
(1) Submit the proposed addenda to the department for review as much in advance of issuing it as possible;
(2) Refrain from issuing the addenda without approval from the department; and
(3) Issue the approved addenda 5 days or more prior to bid opening.