N.H. Admin. Code § Env-Dw 1108.11

Current through Register No. 50, December 12, 2024
Section Env-Dw 1108.11 - Limitations on Project Modifications; Requests for Approval
(a) After construction has commenced, the recipient shall not make, allow, or authorize any changes, modifications, or amendments to, or any departures from, the approved plans and specifications that would materially or significantly affect project cost, estimated revenues, or project design in accordance with Env-Dw 1108.09 without prior written approval from the department.
(b) The recipient shall request such approval by submitting the following information in writing to the department:
(1) The name of the recipient and the name and location of the recipient's water system;
(2) The date of the loan agreement;
(3) A description of the modification(s) for which the recipient is seeking approval;
(4) The reason why the modification(s) are necessary; and
(5) The operational and economic consequences to the water system and to public health and the environment of the department not approving the modifications.
(c) Prior departmental approval of project change orders shall not be required if applicant's project engineer certifies to the department that such change, modification, amendment, or departure:
(1) Will not materially or significantly affect project cost, estimated revenues, or project design; and
(2) Is consistent with the objectives of the project and within the scope of the assistance agreement.

N.H. Admin. Code § Env-Dw 1108.11

(See Revision Note at chapter heading for Env-Dw 1100) #8702, eff 8-24-06

Amended by Volume XXXV Number 06, Filed February 12, 2015 , Proposed by #10772, Effective 1/24/2015, Expires1/24/2025.