Current through Register No. 50, December 12, 2024
Section Env-A 802.09 - Alternative Testing Methods During a TestThe department shall approve deviations from the agreed-upon test method or pre-test protocol only if the following criteria are met:
(a) The owner or operator informs department personnel assigned to the compliance stack test or RATA of the following: (1) The deviation from the testing method or planned operational mode of the source;(2) The reason(s) for the deviation; and(3) The implications of such a deviation; and(b) The owner or operator provides technical justification showing that allowance of such deviation will not affect the accuracy of the compliance stack test or RATA.N.H. Admin. Code § Env-A 802.09
#7788, eff 10-31-02; ss by #9802, eff 10-31-10
Amended by Volume XXXIX Number 19, Filed May 9, 2019, Proposed by #12762, Effective 5/1/2019, Expires 5/1/2029.