N.H. Admin. Code § En 1303.07

Current through Register No. 50, December 12, 2024
Section En 1303.07 - Installation and Maintenance
(a) All attachments shall be installed in accordance with the National Electrical Safety Code, 2017 edition, available as specified in Appendix B, the National Electrical Code as adopted in RSA 155-A:1, IV, and the SR-1421 Blue Book - Manual of Construction Procedures, Issue 6, Telcordia Technologies, Inc., an Ericsson company (2017), available as specified in Appendix B, and in accordance with such other applicable standards and requirements specified in the pole attachment agreement.
(b) The attaching entity shall install and maintain its attachments so as to prevent interference with service furnished by the pole owner or owners and any other attaching entity.
(c) If a pole or existing attachment is not in compliance with applicable standards and codes and is required to be brought into compliance before a new attachment can be added, the cost of bringing that pole or existing attachment into compliance shall not be assessed to or imposed on the entity seeking to add a new attachment.
(d) Neither the cost to remove a duplicate pole that was not removed when a pole was replaced earlier, nor the cost to complete other work started before the make-ready work, shall be assessed to or imposed on the entity seeking to add a new attachment.
(e) An overlash shall not be deemed an attachment and an attaching entity shall have the right to install an overlash subject to the notification provisions of En 1303.06(c).

N.H. Admin. Code § En 1303.07

Derived from Volume XLII Number 49, Filed December 8, 2022, Proposed by #13497, Effective 12/1/2022, Expires 12/1/2032