N.H. Admin. Code § Ed 1008.02

Current through Register No. 44, October 31, 2024
Section Ed 1008.02 - Timeline for IPE Development
(a) The IPE shall be developed as soon as possible, within 90 days of the determination of eligibility pursuant to Ed 1006.
(b) If the NHVR counselor anticipates the IPE development will be delayed, the eligible individual shall be informed of, and the NHVR counselor shall document in the record of services, the:
(1) Reasons for the delay;
(2) Steps necessary to complete the development of the IPE;
(3) Date for which the IPE shall be completed; and
(4) Completion of the "Plan Development Extension" form, June 2021.

N.H. Admin. Code § Ed 1008.02

Derived from Volume XLI Number 32, Filed August 12, 2021, Proposed by #13231, Effective 7/13/2021, Expires 7/13/2031