Section Acp 210.01 - Computation of Time

Any time period specified in an order shall begin with the day following the act, event, or default, and shall include the last day of the period, unless it is Saturday, Sunday, or state legal holiday, in which event the period shall run until the end of the next day which is not a Saturday, Sunday, or state legal holiday. When the period prescribed or allowed is less than 7 days, intermediate Saturdays, Sundays, and state legal holidays shall be excluded from the computation.

N.H. Admin. Code § Acp 210.01

#7081, eff 8-26-99; ss by #7871-A, eff 4-14-03; ss by #10004, INTERIM, eff 9-22-11, EXPIRES: 3-20-12

New. #10157, eff 6/27/2012.