Current through November 8, 2024
1. If an electric utility will require additional time to implement an element of a natural disaster protection plan before the next fire season, the electric utility may request expedited treatment of that element.2. The Commission will issue an order approving or modifying a natural disaster protection plan not later than 180 days after the date on which the plan was submitted.3. At any time after a natural disaster protection plan has been approved and before the date on which a new plan must be submitted pursuant to NRS 704.7983: (a) An electric utility may submit to the Commission a request to amend a natural disaster plan; and(b) Any person may petition the Commission for the modification of a natural disaster protection plan.Nev. Admin. Code § 704.Sec. 8
Added to NAC by Bd. of Exam'rs for Marriage & Fam. Therapists by R085-19A, eff. 2/20/2020NRS 703.025, 704.210, 704.7983