Nev. Admin. Code § 704.9706

Current through November 25, 2024
Section 704.9706 - Conservation and energy efficiency plan: Submission; periodic filing; eligibility of programs to recover costs; order accepting plan or specifying inadequacies
1. A gas utility applying to implement a portfolio of substantive conservation and energy efficiency programs must submit a plan for acceptance by the Commission in conjunction with a general rate case filed pursuant to NRS 704.110 or in an application to implement its conservation and energy efficiency plan filed pursuant to NAC 704.9704.
2. Every 3 years from the date of the final order in which the gas utility's plan was initially accepted, the utility shall file a conservation and energy efficiency plan with an application to implement its conservation and energy efficiency plan that meets the requirements of NAC 704.9704.
3. In the case of a gas utility which also provides electric service, the conservation and energy efficiency plan required in subsections 1 and 2 may be submitted in conjunction with the electric utility's resource plan, as defined in NAC 704.9156.
4. Only substantive conservation and energy efficiency programs in a conservation and energy efficiency plan accepted by the Commission are eligible to recover costs pursuant to NAC 704.9704 and 704.9714.
5. Within 180 days after a gas utility has filed its conservation and energy efficiency plan, unless filed in conjunction with a general rate case, the Commission will issue an order accepting the plan as filed or specifying portions of the plan which the Commission deems to be inadequate.

Nev. Admin. Code § 704.9706

Added to NAC by Pub. Utilities Comm'n by R095-08, eff. 9-29-2008

NRS 703.025, 704.210, 704.992