Section 704.9475 - Analysis of sensitivity for major assumptions and estimates used in resource plan1. A utility shall conduct an analysis of sensitivity for all major assumptions and estimates used in its resource plan. The analysis must include the: (a) Forecast of peak demand and energy consumption;(b) Dates when proposed acquisitions will be in service;(d) Costs of power plants;(f) Amounts of purchased power and corresponding costs;(g) Schedule, impact and costs of programs for energy efficiency and conservation;(h) Capacity of plants in megawatts;(l) Environmental costs; and2. The utility shall state the ranges and consequences of uncertainty for each of the assumptions and describe methods of combining various uncertainties.Nev. Admin. Code § 704.9475
Added to NAC by Pub. Service Comm'n, eff. 6-7-84; A 2-18-88; 3-27-92; A by Pub. Utilities Comm'n by R004-04, 5-25-2004; R042-10, 7-22-2010NRS 703.025, 704.210, 704.741