Nev. Admin. Code § 704.9475

Current through November 25, 2024
Section 704.9475 - Analysis of sensitivity for major assumptions and estimates used in resource plan
1. A utility shall conduct an analysis of sensitivity for all major assumptions and estimates used in its resource plan. The analysis must include the:
(a) Forecast of peak demand and energy consumption;
(b) Dates when proposed acquisitions will be in service;
(c) Unit availability;
(d) Costs of power plants;
(e) Prices of fuel;
(f) Amounts of purchased power and corresponding costs;
(g) Schedule, impact and costs of programs for energy efficiency and conservation;
(h) Capacity of plants in megawatts;
(i) Discount rates;
(j) Rate of inflation;
(k) Cost of capital;
(l) Environmental costs; and
(m) Economic benefit.
2. The utility shall state the ranges and consequences of uncertainty for each of the assumptions and describe methods of combining various uncertainties.

Nev. Admin. Code § 704.9475

Added to NAC by Pub. Service Comm'n, eff. 6-7-84; A 2-18-88; 3-27-92; A by Pub. Utilities Comm'n by R004-04, 5-25-2004; R042-10, 7-22-2010

NRS 703.025, 704.210, 704.741