Nev. Admin. Code § 704.882

Current through November 25, 2024
Section 704.882 - Net metering tariffs: Application for approval; contents

A utility must file an application with the Commission to obtain approval of a net metering tariff. The net metering tariff must include, at a minimum, the following provisions:

1. Net metering must be accomplished using a single meter capable of registering the flow of electricity in both directions, except that if the net metering system of a customer-generator has a capacity of more than 25 kilowatts, the utility may require the customer-generator to install, at his or her own expense or at a cost which is negotiated between the customer-generator and the third-party system owner or operator, an energy meter that is capable of measuring generation output and customer load.
2. Billing for net metering must be made in accordance with the provisions of NRS 704.775.
3. Interconnection with the utility must be consistent with the utility's tariff.
4. The net metering system must meet the standards set forth in NRS 704.774.

Nev. Admin. Code § 704.882

Added to NAC by Pub. Utilities Comm'n by R032-08, eff. 9-18-2008; A by R140-09, 4-20-2010; R083-11, 5-30-2012

NRS 701B.840, 703.025, 704.210, 704.773