Section 704.7976 - Advance application: Dates on which deemed filed or denied

A gas infrastructure replacement advance application must be:

1. Filed on or before June 1 of each calendar year or as otherwise provided by the Commission.
2. Deemed denied if the Commission has not acted within 135 days after the date on which the advance application is filed.

Nev. Admin. Code § 704.7976

Added to NAC by Pub. Utilities Comm'n by R020-13, eff. 2-26-2014

NRS 703.025, 704.210