Nev. Admin. Code § 704.6679

Current through November 25, 2024
Section 704.6679 - Filing requirements for proceeding to establish or change rates

In a proceeding to establish or change its rates, a utility shall file:

1. A study of the cost of service;
2. Illustrative rates for all classes of customers based on the study of the cost of service;
3. A statement of the cost of the gas supplied to the utility;
4. A statement of the cost of the gas supplied to the utility's suppliers;
5. A statement of the utility's projected supply of gas for the 10 years immediately following the proceeding, differentiating between the supplies which are currently under contract and those which are not;
6. A statement of the projected supply of gas of the utility's suppliers during the 10 years immediately following the proceeding, differentiating between the supplies which are currently under contract and those which are not; and
7. A statement of the current prices of alternate fuels for each class of customers, including a projection of those prices for the year following the proceeding.

Nev. Admin. Code § 704.6679

Pub. Service Comm'n, Gen. Order 36 § 4.0, eff. 10-14-82

NRS 703.025, 704.210