Current through October 11, 2024
Section 535.270 - Compliance with terms and conditions of approval; violations1. An applicant who begins construction of a dam pursuant to an application approved by the State Engineer shall: (a) Comply with all terms and conditions imposed by the State Engineer as conditions for approval; and(b) Ensure that all construction conforms to the plans as approved.2. A dam built in violation of this section is not legally established or recognized for the purposes of NRS 535.050, and the State Engineer may order the removal of such a dam pursuant to that section. In addition, if the dam presents an immediate danger, the State Engineer may take the remedial steps authorized in NRS 535.030.Nev. Admin. Code § 535.270
Added to NAC by St. Engineer by R124-02, eff. 5-30-2003NRS 532.120, 535.030, 535.050