Unless the authority to take action is delegated by the Board to the Administrator, an action by the Board is required for:
1. The designation of projects, budgets and priorities to be included in the recommended program for capital improvements;2. The adoption of regulations; and3. Presiding over appeals relating to:(a) The qualification of contractors;(b) The qualification of subcontractors, including, without limitation, the qualification of subcontractors with whom a construction manager at risk intends to enter into a contract; and(c) Disputes regarding contracts.Nev. Admin. Code § 341.015
Planning Bd., Policy, Procedure and Rules §§ 1210 & 1402, eff. 1-20-62; A and renumbered as §§ 1300-1306, 5-3-72; A 11-17-73; 7-16-76; 1-3-78-NAC A 12-16-82; A by Pub. Works Bd., 3-17-94; R096-04, 12-15-2004; R188-07, 4-17-2008; R106-11, 5-30-2012NRS 341.070, 341.110, 341.145, 341.161