Except as provided by law, approval to construct or acquire electric transmission lines carrying more than 700 volts or related facilities shall be obtained from the Nebraska Power Review Board prior to construction or acquisition.
285 Neb. Admin. Code, ch. 2, § 002
ENABLING LEGISLATION;84-909, 70-1006, 70-1011, and 70-1012, R. R. S. 1943.