Section 261-3-009 - PROJECT REPORTING

Projects which are granted financial assistance from the Fund must submit on or before April 1st, an annual report containing information detailing project progress and anticipated progress for the year.

At the time the Applicant completes a project, a Close Out Report will be submitted to the Commission and the Director identifying what the project accomplished and what benefits were achieved. Quantifying and/or explicitly describing the water sustainability benefits, as described in the application, that were or will be achieved by the funding supplied by the Fund is preferred. After project completion/close out, annual reports are no longer required, unless real estate that was acquired as a part of the project is rented or otherwise generates revenue exclusive of park entry fees, city fees or revenue not resulting from the project.

261 Neb. Admin. Code, ch. 3, § 009

Adopted effective 5/21/2018
Amended effective 12/27/2022