256 Neb. Admin. Code, ch. 4, § 007

Current through September 17, 2024
Section 256-4-007 - Separable Components

If a project plan provides that development of the project will take place on two or more land areas not contiguous to each other, the project portion planned for each such land area shall constitute a separable component of the project. Projects for which total project development will take place all on one contiguous land area and separable components of projects of the type described above may also have separable components. A project component shall be deemed to be any distinguishable phase of project development including such phases as land rights acquisition, project construction, and related facilities development. The extent to which such components constitute separable components for any project shall be determined by the Commission after consultation with the Director and the sponsor. In the event that any project is determined to have separable components, the Commission shall take action to identify such separable components and to determine the estimated costs of completing each such component.

256 Neb. Admin. Code, ch. 4, § 007