83 Neb. Admin. Code, ch. 18, § 007

Current through September 17, 2024
Section 83-18-007 - Architectural Design

A copy of all architectural design documents shall be submitted to the Jail Standards Division for review and comment at the following times:

007.01 At the completion of the schematic design phase;
007.02 At the completion of the design development phase; and
007.03 At the completion of working drawings and specifications.

At each submission of key planning and design documents to the Division for review, the architect shall certify, in writing, the plan's compliance with these Standards.

83 Neb. Admin. Code, ch. 18, § 007