229 Neb. Admin. Code, ch. 2, § 007

Current through September 17, 2024
Section 229-2-007
A. For all newly installed boilers built to ASME Section I, when the boiler is completed in the Manufacturer's shop without boiler external piping or the boiler external piping was not hydrostatically tested at the shop, subsequent hydrostatic testing of the boiler external piping shall be the responsibility of any holder of a valid ASME Certification Mark with the "S", "A", or "PP" designator. The hydrostatic test shall be conducted in accordance with the requirements of ASME Section I, PG-99.
B. All new field assembled boilers built to ASME Section IV that bear the "H" designator shall meet the requirements in ASME Section IV, HG-532 and HG-533. All field assembled Cast Iron boilers shall be hydrostatically tested in accordance with ASME Section IV, HC-410. This test shall be documented on the State of Nebraska NE-R-1 Report of Non-Welded Repairs and Hydrostatic Tests.
C. All boilers and pressure vessels that require further field fabrication of the pressure boundary parts by welding shall be completed, hydrostatically tested and certified in accordance with the original code of construction.

229 Neb. Admin. Code, ch. 2, § 007

Amended effective 8/7/2016.