153 Neb. Admin. Code, ch. 17, § 001

Current through September 17, 2024
Section 153-17-001 - Tank Installation Permit
001.01 Owners/operators shall obtain an installation permit for all new and replacement tank and piping installations.
001.0lA. Applications for installation permits shall be provided by and filed with the State Fire Marshal's office. Submission of a detailed site plan and a $ 50.00 inspection fee must be made at least ten (10) working days prior to the proposed installation. The $ 50.00 fee is per installation, regardless of the number of tanks involved.
001.0lB. Tank installations shall meet all the applicable criteria set out in the NFPA codes promulgated by the State Fire Marshal.
001.0IC. Notification of date and time of Installation shall be given to the State Fire Marshal Flammable Liquids Division at least 24 hours prior to installation.

153 Neb. Admin. Code, ch. 17, § 001