Where a permitted facility is found to be out of compliance a reissued or modified permit may specify a schedule of compliance which shall require compliance as soon as possible but where a schedule exceeds one year from the date of permit issuance, the schedule shall set forth interim requirements and the dates for their achievement.
No later than fourteen (14) days following each interim date and the final date of compliance, the permittee shall notify the Director in writing of its compliance or noncompliance with the interim or final requirements or submit progress reports.
126 Neb. Admin. Code, ch. 2, § 011