124 Neb. Admin. Code, ch. 3, § 006

Current through September 17, 2024
Section 124-3-006 - Operating Permit
006.01 An operating permit may be issued when construction that complies with the approved construction permit documents has been completed and:
006.01A The Professional Engineer who designed the system submits a completed form provided by the Department which notifies the Department of construction completion
006.01B The system registration form, system registration fee, and any applicable late fee have been received by the Department.
006.02 The Department may require, as an operating permit condition, groundwater monitoring for any onsite wastewater treatment system if there is a potential for groundwater pollution.
006.03 The Department may require, as an operating permit condition, implementation of a Department approved operation and maintenance plan to ensure proper operation of the onsite wastewater treatment system.
006.04 The permittee will operate and maintain the onsite wastewater treatment system in compliance with any permit conditions, these regulations and the Nebraska Environmental Protection Act §§ 81-1501 et seq.

124 Neb. Admin. Code, ch. 3, § 006

Amended effective 6/27/2022