Rule 36.14.403 - APPLICATION CONTENT - RESERVOIR OPERATION PLAN(1) Any application for a permit to operate a high-hazard daM must include a documented plan of the dam and reservoir operation for normal conditions, flood events, and emergency conditions. This plan must include: (a) the operation procedures;(b) maintenance procedures; and(c) emergency procedures and warning plan.Mont. Admin. r. 36.14.403
NEW, 1988 MAR p. 2489, Eff. 11/24/88.Sec. 85-15-110, MCA; IMP, Sec. 85-15-212, MCA;