Current through Register Vol. 23, December 6, 2024
Rule 36.14.205 - APPLICATION PROCESSING PROCEDURES(1) The department shall:(a) notify the owner in writing within 10 days of receipt that an application has been received and advise the owner of any additional information required to complete the application;(b) classify the hazard of the dam or reservoir based on the application, the site inspection, and evaluation of the potential flooded area caused by a dam failure; and(c) notify the owner in writing of the hazard classification determination within 60 days of receipt of a complete application.Mont. Admin. r. 36.14.205
NEW, 1988 MAR p. 2489, Eff. 11/24/88; AMD, 2024 MAR p. 2065, Eff. 8/24/2024AUTH: 85-15-110, MCA; IMP: 85-15-209, MCA