Current through Register Vol. 23, December 6, 2024
Rule 12.10.104 - REIMBURSEMENT OF COSTS(1) All billing on a proposed project must be completed by June 15 of the fiscal year the money is awarded.(2) Reimbursement requests will be based upon actual costs or in-kind contributions, verified by receipts and documentation that the work was completed.(3) With prior approval, the department will consider situations where work cannot be completed until funds are received. Which situations constitute a special circumstance or hardship, requiring dispersal of grant funds in advance, is at the department's discretion.(4) Per 87-1-278, MCA, existing assets and shooting range developments may not be applied to the matching funds or in-kind contributions. Existing assets and shooting range developments are fixed improvements to the shooting range owned or made prior to the application deadline.
Mont. Admin. r. 12.10.104
NEW, 1992 MAR p. 1143, Eff. 5/29/92; AMD, 2003 MAR p. 1986, Eff. 9/12/03; AMD, 2014 MAR p. 2453, Eff. 10/10/14.