Mo. Code Regs. tit. 7 § 10-24.140

Current through Register Vol. 49, No. 23, December 2, 2024
Section 7 CSR 10-24.140 - Tradeoffs in Design-Build Contracting

PURPOSE: This rule describes when and how tradeoffs should be used in awarding a design-build contract and documentation of the tradeoff decisions.

(1) At its discretion, the commission may consider the tradeoff technique when it is desirable to award to other than the lowest priced proposer or other than the highest technically rated proposer.
(2) If the commission uses a tradeoff technique, the following is to be clearly stated in the solicitation:
(A) All evaluation factors and significant subfactors that affect contract award and the factor's relative importance ; and
(B) Whether all evaluation factors other than cost or price, when combined, are:
1. Significantly more important than cost or price; or
2. Approximately equal in importance to cost or price; or
3. Significantly less important than cost or price.
(3) When tradeoffs are performed, the source selection records must include the following:
(A) An assessment of each proposer's ability to accomplish the technical requirements; and
(B) A summary, matrix, or quantitative ranking, along with appropriate supporting narrative, of each technical proposal using the evaluation factors.

7 CSR 10-24.140

AUTHORITY: sections 226.020, RSMo 2000 and 226.030 and 227.107, RSMo Supp. 2004.* Original rule filed Aug. 15, 2005, effective Feb. 28, 2006.
Amended by Missouri Register June 15, 2018/Volume 43, Number 12, effective 7/31/2018

*Original authority: 226.020, RSMo 1939; 226.030, RSMo 1939, amended 1965, 2003, 2004; and 227.107, RSMo 2002.