Current through Register Vol. 49, No. 23, December 2, 2024
Section 10 CSR 1-3.010 - Consolidation of Permit ProcessingPURPOSE: This amendment removes unnecessary requirements specifying how the department and a permittee will comply with section 640.017, RSMo, and provides flexibility when the consolidated permitting process is used.
(1) Whenever a facility or activity requires more than one (1) environmental permit administered by the department, an applicant may request, or the department may offer, a unified permitting schedule that covers the timing and order to obtain such permits, as provided in section 640.017, RSMo. Upon agreement between the applicant and the department, the processing of permit applications would then be administered pursuant to that section. AUTHORITY: section 640.017, RSMo Supp. 2009.* Original rule filed Sept. 24, 2009, effective 5/30/2010 . Amended by Missouri Register January 2, 2019/Volume 44, Number 1, effective 2/28/2019*Original authority: 640.017, RSMo 2008.