In order to allow the Department to perform a technical and loan allowability review, requests for change order approvals must conform to Department guidance, requirements and regulations.
Change orders which include time extensions exceeding 30 days beyond the original contract completion date, and/or documentation that the loan recipient is implementing all legal remedies provided in the contract documents for failure to complete construction when required, must be submitted to the Department as specified in Rule 3.7.7(9) of these regulations. Justification for contract time extensions included in a change order must be prepared, but need not be submitted to the Department unless the total time extensions for the contract exceed 30 days after the original contract completion date, in which case justification for all time extensions must be submitted to the Department for an allowability determination.
33 Miss. Code. R. 2-3.7.5