No contract requiring PSCRB approval is transferable or otherwise assignable without the prior approval of the PSCRB; however, a contractor may assign monies receivable under a contract after due notice to the State and the contracting entity, and with the approval of the PSCRB.
When, in the best interest of the State, a successor in interest may be recognized in a novation agreement, the transferor and the transferee must agree that:
When a contractor requests to change the name in which it holds a contract with the State, the agency shall, upon receipt of a document indicating such change of name (for example, an amendment to the articles of incorporation of the corporation), enter into an agreement with the requesting contractor to effect the change. The agreement changing the name shall specifically indicate that no other terms and conditions of the contract are changed. This change must be approved by the PSCRB.
27 Miss. Code. R. 100-3-103