Factory-Built homes shall not be skirted until a duly authorized representative of the Factory-Built Home Division of the State Fire Marshal's Office has inspected the set-up. An inspection of the home is usually scheduled to occur within three (3) to five (5) business days following the receipt of the Property Locator/Certificate of Installation from the retailer, the developer and/or the installer/transporter. If, at the time of the installation inspection, the skirting has already been installed, it will be necessary to reschedule the inspection until such time that the skirting can be removed for an unobstructed view of the underside of the home. The person(s) removing the skirting shall contact the State Fire Marshal's Office when the home is ready for the inspection to be conducted.
19 Miss. Code. R. 7-5.03.3.3