12 Miss. Code. R. 3-20-800.29

Current through December 10, 2024
Section 12-3-20-800.29 - BID PROTEST

When all Proposals have been read and recorded, should a Bidder wish to protest, the Bidder should rise and announce to all present the protest. All protest, after being made verbally, must be made in writing to the Bureau no later than twenty-four (24) hours following the bid opening.

The letter of protest should be addressed to the Bureau of Building, Grounds and Real Property Management's Director. It should identify the Project, include what is being protested, why it is being protested, and be signed by the individual who is protesting.

Protestors may be required to appear at the next PPRB meeting and personally present their protest. The Bureau is under no obligation to consider any protest received after twenty-four (24) hours. This includes a protest made by anyone regardless of whether they attended the bid opening.

12 Miss. Code. R. 3-20-800.29

Adopted 11/25/2016
Amended 3/15/2021