Section 12-3-20-700.6 - OWNER/PROFESSIONAL/CONTRACTOR RELATIONSHIP

The Professional will be the Owner's representative during construction and until the expiration of the Warranty period. The Professional will make on-site inspections as necessary to protect the interest of the Owner and to guard the Owner against defects and deficiencies in the Work of the Contractor. All instructions to the Contractor will go through the Professional.

The Owner is also represented by the Bureau's Project Manager who make regular on-site inspections of the Work. If the Using Agency is occupying the building during construction, the Project Manager will coordinate with the Contractor and Using Agency a schedule for vacating areas as the Contractor requires.

The Contractor's Superintendent is responsible for the coordination of the total construction Project. All Subcontractors will cooperate with the Superintendent so as to facilitate the progress of the Work. Each trade will afford all other trades every reasonable opportunity for the installation of their work. The Contractor will receive all instructions from the Professional.

12 Miss. Code. R. 3-20-700.6

Adopted 11/25/2016
Amended 3/15/2021