The Bureau will schedule regular Progress meetings at the time of the Pre-construction Conference where the Owner's Project Manager, Professional and his Consultants, and Subcontractors pertinent to the agenda will attend. The Contractor will prepare the agenda to include:
1. Review, approve minutes of the previous meeting2. Review work progress since last meeting3. Note field observations, problems and decisions4. Identify problems which impede planner progress5. Review off-site fabrication problems6. Revise construction schedule as indicated7. Plan progress during the next work period8. Review proposed changes9. Complete other current business10. Review application for payment submitted by the Contractor12 Miss. Code. R. 3-20-700.17