The Design Development Documents consist of a written report and detailed drawings based on approved Schematic Design documents. The following paragraphs set forth general requirements for the Design Development phase and the submission of required data.
The Design Development Phase is specific and detailed in nature by comparison to the Schematic Design Phase. The project design concept is further developed so most decisions and details regarding the entire facility are resolved. Reviews of the Design Development submission should resolve all questions. In many cases, Design Development Documents are the beginning of the Construction Document Phase because the drawings and specifications submitted are the partially competed Contract Documents.
The Professional will prepare and submit to the Bureau two (2) sets of drawings which shows allocation of space and overall dimensions, adequate explanation of HVAC, electrical and structural systems, miscellaneous equipment, lists and schedules. In addition, site plans including topography, adjacent buildings and utilities will be submitted.
The Professional will prepare two (2) sets of preliminary specifications following the Construction Specification Institute [CSI] and give basic descriptions of essential building materials, finishes, components, and systems. Cost estimates reflecting the total budget including construction, furniture and equipment, fees and contingency will be submitted.
The Design Development Documents will also be furnished to the Using Agency and its Governing Board for review. If the Using Agency or Governing Board has any comments regarding the Documents, these comments should be forwarded to the Bureau through written correspondence.
The Using Agency, Governing Board and Review by Others (where applicable) will approve each design Phase and notify the Bureau in writing of such approval. Upon approval of the Design Development phase by the Bureau, the Professional will be notified in writing to proceed with the Construction Document phase.
12 Miss. Code. R. 3-20-600.18