Section 12-3-2.1-700.5 - PRODUCT LISTING

Within thirty (30) days after the signing of the Contract, the Contractor will submit to the Professional five (5) copies of a complete list of all products which are proposed for installation. The list should be tabulated by specification section.

Within thirty (30) days after the signing of the Contract, the Contractor will submit to the Professional five (5) copies of a list indicating all products he proposes for substitution. This list should include:

1. Complete information substantiating the substituted product meets the specifications
2. Product:
a. Product identification (name and address)
b. Manufacturer's literature (product description, performance/test data, reference standards)
c. Samples
d. Name and address of similar projects on which product was used and date of installation
3. Construction Methods:
a. Detailed description of proposed method
b. Drawings illustrating methods
4. Itemized comparison of proposed substitution with product or method specified
5. Data relating to changes in construction schedule
6. Accurate cost data on proposed substitution in comparison with product or method specified

Product List

* Manufacturer's name and address

* Trade name

* Model or catalog designation

* Manufacturer's data

* Performance and test data

* Reference standards