12 Miss. Code. R. 3-2.1-700.35

Current through December 10, 2024
Section 12-3-2.1-700.35 - FINAL INSPECTION

Upon completion of the Project, the Contractor will notify the Professional who will make an inspection and compile a list of deficiencies. If, in the Professional's judgement the Project is not ready for final inspection, another inspection will be scheduled.

The Owner's inspection will follow after all known deficiencies have been corrected and the Professional determines the Project is ready. The Professional will call for a group inspection of the Project with the Bureau, the Using Agency, and its governing board for the express purpose of determining the Contractor's compliance with the Contract Documents.

It is the responsibility of the Professional to determine, arrange and notify those needing to be present of the date, place and time of the final inspection including all applicable federal governmental agency representatives. The date and time of the final inspection will be set for the convenience of the Bureau, the Using Agency and its Governing Board.

One (1) week prior to the final inspection, written notice will be furnished to all parties listed above. The Professional will conduct the final inspection in the presence of those listed above and will tabulate a complete list of defects or discrepancies, if any, to be correction by the responsible parties.

Copies of the punch list will be furnished to all parties concerned. Once the corrections are made, the Professional will schedule a second inspection at the convenience of the Bureau. Final inspection will not be scheduled until all Work is completed or unless otherwise approved by the Bureau in writing. Upon completion of all punch list items, the Professional will provide a letter recommending acceptance to the Bureau with a copy to the Using Agency and its Governing Board.

12 Miss. Code. R. 3-2.1-700.35

Amended 8/14/2016