12 Miss. Code. R. 3-2.1-600.21

Current through December 10, 2024
Section 12-3-2.1-600.21 - COST ANALYSIS

Cost estimates reflecting the total budget including construction, furniture and equipment, fees and contingency will be submitted based on detailed plans and specifications. The basis of the cost estimate will be a preliminary quantity survey showing the escalation projects from the date of the estimate to the projected bid date for the building systems noted on the right.

Building Systems

* Structure

* Foundation

* Floor grade and systems

* Roof

* Exterior/interior walls/partitions

* Interior finishes

* Sight lines

* Stairs and elevators

* Specialty items

* Mechanical systems

* Electrical systems

* Built-in equipment

* Site construction

For a suggested Project Budget Estimate format see Appendix 600.

12 Miss. Code. R. 3-2.1-600.21

Amended 8/14/2016