12 Miss. Code. R. 3-2.1-1-01310-1.01

Current through December 10, 2024
Section 12-3-2.1-1-01310-1.01 - DESCRIPTION
A. Scope: Provide projected construction schedules for entire work and revise periodically. The following is a minimum requirement and other type schedules are acceptable with Owner's approval. This type of schedule is acceptable for any Project whose initial Contract award amount if less than one (1) million dollars ($1,000,000).
B. Form of Schedules: Prepare in form of horizontal bar chart.
1. Provide separate horizontal bar column for each trade or operation.
2. Place in order of the Table of Contents of Specifications.
3. Identify each column by major Specification section number.
4. Identify the first work day of each week by horizontal time scale.
5. Scale and space to allow for updating.
C. Contents of Schedule:
1. Provide complete sequence of construction by activity.
2. Indicate dates for beginning and completion of each stage of construction.
3. Identify work of separate floors, separate phases, or other logically grouped activities.
4. Show projected percentage of completion for each item of work as of first day of month.
D. Updating:
1. Show all changes occurring since previous submission of updated schedule.
2. Indicate progress of each activity and completion dates.
E. Submittals:
1. Submit initial schedules to the Professional within fifteen (15) days after date of Notice to Proceed.
2. Submit to Professional periodically updated schedules accurately depicting progress to first day of each month.
3. Submit two (2) copies, one (1) to be retained by the Professional and the other forwarded to the Owner.

12 Miss. Code. R. 3-2.1-1-01310-1.01