Rule 11-6-3.5 - Operator Responsibilities
A. Certified operators in charge of wastewater facilities must personally visit said facilities at a sufficient frequency and duration to perform such tasks as may be required by the permit and to ensure proper operation and management of said wastewater facilities. Unless otherwise stated in the facility's permit or an order of the Commission, certified operators in charge of wastewater facilities shall visit the facilities, as a minimum, according to the following schedule:

Class I Facility

One (1) day per week

Class II Facility

Two (2) days per week

Class III Facility

Three (3) days per week

Class IV Facility

Five (5) days per week

B. Certified operators in charge of wastewater facilities shall be thoroughly familiar with all monitoring and reporting requirements mandated by the facility's permit and shall ensure said facility complies with these requirements.
C. Certified operators in charge of wastewater facilities must maintain written documentation of each facility visit. Documentation of facility visits shall be made available to the Department upon request.

11 Miss. Code. R. 6-3.5

Miss. Code Ann. §§ 21-27-201, et seq., 49-2-1, et seq. and 49-17-1, et seq.