Minn. R. agency 175, ch. 8830, RAIL SERVICE IMPROVEMENT, pt. 8830.5690

Current through Register Vol. 49, No. 24, December 9, 2024
Part 8830.5690 - REQUEST FOR INFORMATION

The commissioner shall direct requests for information under the authority of Minnesota Statutes, section 222.54, to the corporate office of the rail carrier. The commissioner's requests will specify the kind of information, the level of detail needed, and the required date of submittal.

Within 20 days from the receipt of the request, the rail carrier, if necessary, may apply for a revision of the time schedule for preparing the information. The commissioner shall approve or disapprove the requests.

If the requested information is not received within the time schedule, the commissioner may make a final demand. The final demand must be in writing and sent by certified mail to the corporate office of the rail carrier. If the information is not received within 60 days of the receipt of the final demand, the commissioner may issue a subpoena to compel production of the information.

Minn. R. agency 175, ch. 8830, RAIL SERVICE IMPROVEMENT, pt. 8830.5690

23 SR 524

Statutory Authority: MS s 218.071; 219.073; 219.165; 219.17; 219.384; 222.50; 222.58; 222.63