Minn. R. agency 167, ch. 7090, pt. 7090.2060

Current through Register Vol. 49, No. 19, November 4, 2024
Part 7090.2060 - SUBDIVISION OWNER REGISTRATION

For a construction site that is covered under an existing construction storm water permit where the owner or operator changes, the new owner or operator must:

A. obtain a permit and develop and implement the storm water pollution prevention plan; or
B. submit to the commissioner a subdivision registration form provided by the agency within seven days of assuming operational control of the site, conducting construction activity on their portion of the site, or of legal transfer, sale, or closing on the property, and:
(1) implement the provisions of the site's original storm water pollution prevention plan for the portion of the site which the construction activities will impact; or
(2) develop and implement a storm water pollution prevention plan for the portion of the site which the construction activities will impact according to the requirements of the construction storm water permit for the site.
C. The new owner or operator must comply with all applicable requirements of the permit and the storm water pollution prevention plan.
D. The new owner or operator must ensure that activities do not render another party's erosion prevention and sediment control BMP's ineffective.

Minn. R. agency 167, ch. 7090, pt. 7090.2060

30 SR 125

Statutory Authority: MS s 115.03