An annual water appropriation processing fee shall be submitted for each water appropriation permit in force at any time during the year. The fees are required whether or not the permittee appropriated or used any water as authorized by permit during the year.
The fee shall be based on the following schedule:
A notice of the fees owed will be mailed to the permittee, with the reporting forms, by the commissioner.
The fee, with accompanying report, for the calendar year's appropriation or use of water, shall be sent to the commissioner no later than February 15 of the following year.
Failure to pay the fee shall be sufficient cause for terminating a permit 30 days following written notice by the commissioner.
The effective date of this part is August 1, 1985.
Minn. R. agency 158, ch. 6115, PERMIT, INSPECTION, AND MONITORING FEES, pt. 6115.0110
Statutory Authority: MS s 105.44