Part 1305.0403 - SECTION 403, HIGH-RISE BUILDINGSSubpart 1.IBC section 403.2.1.2.IBC section 403.2.1.2 is deleted in its entirety.
Subp. 3.IBC section 403.4.8.3.IBC section 403.4.8.3 is amended to read as follows:
403.4.8.3Standby power loads. The following are classified as standby power loads: 1. power and lighting for the fire command center required by Section 403.4.6;2. ventilation and automatic fire detection equipment for smokeproof enclosures; and3. passenger elevators serving occupied floors more than 75 feet (22, 860 mm) above the lowest level of fire department vehicle access.Minn. R. agency 151, ch. 1305, pt. 1305.0403
27 SR 1474; 32 SR 7; L 2007 c 140 art 4 s 61; art 13 s 4; L 2008 c 337 s 64; 39 SR 1605; 44 SR 610 eff. 3/31/2020Statutory Authority: MS s 16B.37; 16B.59 to 16B.76; 326B.101 to 326B.194