Minn. R. agency 141, ch. 4410, EXPLORATORY DRILLING FOR THE DISPOSAL OF HIGH-LEVEL RADIOACTIVE WASTE, pt. 4410.7920

Current through Register Vol. 49, No. 24, December 9, 2024
Part 4410.7920 - DRILL HOLE CONSTRUCTION STANDARDS

A permittee shall comply with the following standards with respect to construction of a drill hole.

A. Drill holes shall be constructed in such a fashion as to facilitate testing and prevent any contamination of aquifers.
B. Drill holes not permanently abandoned within 30 days of completion must be constructed to meet the requirements of part 4727.1100 regarding temporary abandonment of exploratory borings, and the requirements of any federal statutes and regulations applicable to deep wells.

Minn. R. agency 141, ch. 4410, EXPLORATORY DRILLING FOR THE DISPOSAL OF HIGH-LEVEL RADIOACTIVE WASTE, pt. 4410.7920

10 SR 2290

Statutory Authority: MS s 116C.724