Minn. R. agency 138, ch. 7852, PIPELINE ROUTE SELECTION PROCEDURES, pt. 7852.0900

Current through Register Vol. 49, No. 24, December 9, 2024
Part 7852.0900 - APPLICATION ACCEPTANCE NOTICE

Within 20 days of commission acceptance of an application for a pipeline routing permit under part 7852.2000, subpart 4, the commission shall provide published notice of acceptance of the application in a newspaper in each county in which a route is proposed by the applicant.

The notice must include:

A. identification of the applicant;
B. the date of the commission's acceptance of the application;
C. a brief description of the proposed facility including but not limited to size and type;
D. a map showing the routes proposed in that county;
E. the name and function of the public adviser and the address and telephone number where that person can be reached;
F. locations where the pipeline routing permit application is available to the public;
G. procedures for proposing alternate routes; and
H. notice of public information meetings.

Minn. R. agency 138, ch. 7852, PIPELINE ROUTE SELECTION PROCEDURES, pt. 7852.0900

13 SR 2046; L 2005 c 97 art 3 s 19

Statutory Authority: MS s 116I.015; 216G.02