In the rare situation where immediate action by a pipeline company whose pipeline system requires the immediate construction of a pipeline is considered essential to avoid or eliminate an imminent threat, prevent injury, loss of life, property damage, or loss of essential public services, a pipeline project may be undertaken without the review that would otherwise be required by this chapter.
The pipeline company shall notify and demonstrate to the commission, either orally or in writing, that immediate action is essential and must receive temporary authorization from the commission to proceed. All oral requests must be followed by a written request within three working days. Temporary authorization to proceed must be determined by the commission as soon as possible after the request is made and must be limited to only those aspects of the project necessary to control the immediate impacts of the emergency.
Minn. R. agency 138, ch. 7852, EMERGENCY PROCEDURES, pt. 7852.0400
Statutory Authority: MS s 116I.015; 216G.02