Minn. R. agency 138, ch. 7835, DISPUTES, pt. 7835.4500

Current through Register Vol. 49, No. 29, 2025
Part 7835.4500 - COMMISSION DETERMINATION

In case of a dispute between a utility and a qualifying facility or an impasse in the negotiations between them, either party may request the commission to determine the issue. When the commission makes the determination, the burden of proof must be on the utility.

Minn. R. agency 138, ch. 7835, DISPUTES, pt. 7835.4500

9 SR 993

Statutory Authority: MS s 216A.05; 216B.08; 216B.164