When the commissioner approves, disapproves, or modifies a program, project, or evaluation plan, the commissioner shall set forth the reasons in a written decision within 30 days from the date comments are due on the department staff's proposed decision specified under part 7690.1000. The commissioner's decision must include explicit participation, and energy-savings and demand-savings goals for each utility as applicable. If the commissioner's decision will not be issued within this 30-day period, the department shall notify the parties on the service list specified in part 7690.0800 of the date by which a decision will be issued.
Minn. R. agency 120, ch. 7690, pt. 7690.1300
Statutory Authority: MS s 216B.08; 216B.241