Mich. Admin. Code R. 281.54

Current through Vol. 24-24, January 15, 2025
Section R. 281.54 - Principal use; application procedure

Rule 4.

(1) An application for a principal use shall be submitted and processed pursuant to all the following:
(a) An application for a principal use shall be completed by the applicant on a form provided by the department and submitted to the zoning administrator. A completed application shall contain all of the following:
(i) A completed application form signed by the applicant or the applicant's representative.
(ii) A site plan that meets the requirements of R 281.56.
(iii) Evidence of ownership or a legal interest in the property affected by the application for a principal use, or authorization from the property owner to apply for a principal use.
(b) Within 21 days of receipt of an application for a principal use, the zoning administrator shall notify the applicant of the need for additional information, if applicable.
(c) Within 30 days of receipt of a completed zoning permit application, the zoning administrator shall determine if a permit shall be issued. Approved zoning permits shall be forwarded to the applicant with an approved site plan by the zoning administrator. If the zoning administrator determines a zoning permit shall not be issued, the reason shall be provided to the applicant in writing.
(d) Before commencing construction of a principal use, an applicant shall display the approved zoning permit and site plan in a location easily visible from the nearest street or roadway until the authorized project is completed.
(e) A zoning permit is valid for 2 years and is not transferable. All structures shall be completed within 2 years from the date of issuance of the zoning permit.

Mich. Admin. Code R. 281.54

1979 AC; 2013 AACS