Mich. Admin. Code R. 460.986

Current through Vol. 24-21, December 1, 2024
Section R. 460.986 - Insurance

Rule 86.

(1) An applicant interconnecting a level 1 or 2 project to the distribution system of an electric utility may not be required by the electric utility to obtain any additional liability insurance.
(2) An electric utility shall not require an applicant interconnecting a level 1 or 2 project to name the electric utility as an additional insured party.
(3) For a level 3 project, the applicant shall obtain and maintain general liability insurance of a minimum of $1,000,000.
(4) For a level 4 project, the applicant shall obtain and maintain general liability insurance of a minimum of $2,000,000.
(5) For a level 5 project, the applicant shall obtain and maintain general liability insurance of a minimum of $3,000,000.
(6) For level 3, 4, and 5 projects, the electric utility may describe in its interconnection procedures required terms and conditions that must be specified in the general liability insurance.

Mich. Admin. Code R. 460.986

2023 MR 8, Eff. 4/25/2023